services

Pool Construction

Request an estimate

Our swimming pool construction process
from start to finish

Your pool design is now complete and now it's time to start building your Agua Pool! Our team is working behind the scenes to secure permits, schedule inspections, coordinate our equipment and crews and more. We will always keep you informed throughout the entire pool construction process to your Florida pool.

1

Pool site area prep

Once the permits have been issued, your property will be pre-sited for construction by one of our Construction Managers. Our excavator will strip the sod in the pool and deck area.

2

Layout & excavation

Your pool will be laid out using stakes and wooden forms, with the forms representing the outer edge of the pool shell. The forms must not be disturbed, as they represent the exact elevation, location, size, shape, and position of the finished pool. We will alsoThe excavation process is now ready to begin. The earth from your pool is either hauled away or kept on site for backfilling as necessary for later phases of construction. This is one of the two “dirty and noisy” phases of construction. We attempt to keep the dust down to a minimum, but it will be dusty, and the heavy equipment is noisy. We suggest you keep all windows and doors closed and keep your children away from the site during this phase.

3

Plumbing, steel, electrical & inspections

PLUMBING: Schedule 40 PVC pipe, which will be beneath the deck will be installed and extended to the mechanical equipment location. This includes lines such as the main drain, skimmer, hydro-therapy jets, automatic cleaner, waterfall, and any other mechanical lines that may be included in your design. All piping is pressure tested prior to gunite placement to insure against any leaks.
STEEL – 3/8″ steel reinforcing bars are placed to strengthen the gunite shell. The steel is shaped to the pool’s design and extra steel is used at points of high stress. The reinforcing steel is securely tied in place. The day of guniting, the bars are blocked up from the dirt so the entire “basket” will be surrounded by gunite when finished. The electrical contractor will then bond the steel shell. Stairs and benches in the shallow end do not have steel placed; they are solid gunite.
ELECTRICAL – Our licensed electricians will inspect your service panel and determine the exact distance to the mechanical location. They will also bond the steel structure and call in your 1st inspection.
INSPECTIONS – Our office staff will notify both the building and electrical departments, prior to guniting your pool. We have placed your permits in a permit box and erected it in front of your home. Please make sure the building permit box is accessible for the inspectors. If the permit box is not there, please notify us immediately.

4

Gunite

This is the major step in your construction project, one of the dirtiest and certainly the noisiest. There are many large trucks on site the day the Gunite is shot. It’s exciting to watch, but you will want to keep all nearby doors and windows closed throughout the guniting operation. During this phase the stairs, benches, lighting outlets and other features will be set in place. Beginning the next day, we ask that you wet down the gunite shell two twice (2) times per day for seven (7) days to facilitate the curing process. Please don’t be alarmed if any water accumulates in the bottom of the pool. During the seven (7) day curing period 85% of the concrete cure takes place, and we then resume the construction process. The forms will be stripped, any necessary backfilling performed, and preliminary deck grading will take place.

5

Grading

During the grading process we will add any sub-base material needed for the deck area to achieve proper elevation, and all the plumbing, electrical, and gas lines will be laid out at this time.

6

Tile, coping & water features

A 6″ band of ceramic tile will be applied to the top inside edge of your pool which will allow easy cleaning at the pool water line. If tile markers are to be placed on the stairs, they will be done day of plaster. Pleas make sure water and electricity are available for our crew’s use.If your pool design calls for coping, field stone or other materials, our stone masons will install this finish. Otherwise, the cantilever edge of the deck will provide the pool’s top finish. If your pool has a water feature(s) don’t be alarmed if you only see a pile of rocks. The finishing touches have not been applied yet.

7

Deck layout & deck pour

This is a very important phase of the build as your deck will accent both your pool and your home, and at this point your pool and pool area is beginning to take shape and the project really starts to come to life.During the Deck Layout and Pour there will be large concrete trucks in and around your home, and we ask that all cars are cleared to allow access and that all children are kept out of the area. At this point your choice of decking (plain, exposed aggregate, pavers or stamped) will be installed. Some of materials are installed over several days, so please don’t be alarmed if your deck doesn’t look the right color after it is poured. We will also cut expansion joints in the stamped pattern, and you may see some hairline cracks, but the deck is reinforced with 3/8” steel rebar and this is normal.

8

Pool equipment

Your pool equipment, including the filter system, time clock, automatic cleaner, and heater (if ordered), will be installed and our electrician will complete the wiring of all the mechanical equipment.

9

Interior finish

The final step will be applying the interior finish to the pool—and it is essential that the pool and surrounding area be kept as clean as possible. Please be aware that that at this time any work you or other contractors may be undertaking in the pool area which creates dirt, dust, smoke or other debris, must be completed beforehand, or postponed until later. The sparkling cleanliness of a fine quality pool depends not only upon the ability of our craftsmen, but in keeping the pool as clean as possible until it is filled. We cannot be responsible for footprints or stains caused by dirt, fertilizer, dust, and other debris from construction, landscape projects or winds. After the interior finish is applied, either your fence or temporary fence will be installed to meet both local and state codes prior to filling the pool.

10

Filling the pool

Once the filling operation has begun, PLEASE DO NOT turn off the water or move the hose from its original position until the level has risen to the middle of the tile band. This eliminates the possibility of a dirt ring, which is difficult to remove. When the pool is full, please turn off the water and inform us. Under normal conditions it is not necessary to call us until the pool is full. There is no harm in not having the filter on, for up to a week after filling. There is also no harm in swimming in the pool before the filter is started.

11

Completion

We’re almost done!Our project manager will perform a complete quality assurance check to insure everything related to your pool is perfect, AND, we will even take you to “Pool School” to learn how to operate your Agua Pool.

Excellence through ownership and partnerships

At Agua Pools, we take pride in our commitment to delivering exceptional aquatic experiences, and a key factor in our success lies in our strategic approach to equipment management. Unlike many in the industry, Agua Pools distinguishes itself by owning a majority of its cutting-edge pool equipment. This deliberate choice ensures that we have direct control over the quality and reliability of the tools and machinery used in every project we undertake.

Our dedication to excellence extends beyond mere ownership; Agua Pools places significant emphasis on collaboration with trusted partners. By fostering relationships with leading suppliers and manufacturers, we gain access to the latest innovations and industry advancements. This collaborative approach enables us to stay at the forefront of pool technology, offering our clients the most efficient, sustainable, and state-of-the-art solutions available. Whether it's pumps, filtration systems, or automation technologies, Agua Pools combines ownership and strategic partnerships to elevate the standards of pool design, construction, and maintenance.

SPA CONSTRUCTION

Enhance your backyard with a
custom Agua Pools' spa

Experience the added health benefits and outdoor experience with a spa

We can incorporate and build your spa as part of your Agua Pool, or as an altogether separate project. The design options for spas are as varied and limitless as the options for a custom Agua Pool. You can experience paradise and relax in your pool and spa all year around. Enjoy the warm water while letting go of your daily stress or just enjoy listening to the soothing sounds of the water and watching the beautiful colors of the lights.

Looking for design inspiration
for your next project?

Visit one of our 3 display centers conveniently located across Central and North Florida

Find a display center

Additional pool & spa features

When you are in the swimming pool design phase, make sure to include these awesome pool and spa features

Beach entries

Aguagevity

Deck jets

Fountains

Pool lighting

Swim up bars

We would love to get in touch with you about your swimming pool needs.
Fill out the form below and a member of the Agua Pools team will reach out!